Craig J. Opperman P.E., Scioto County Engineer, announced the work schedule for the week of July 23-27, 2012, for his office.

Installing Concrete Pipes

Carey’s Run-Pond Creek Road– CR-49 at the 8.41 mile marker in Union Township will be closed Monday, July 23, through Wednesday, July 25, both day and night. The location of the closure is between Noel Road and Swords Road. County Engineer’s Crews will be installing a concrete pipe.

Cramer Road– CR-135 at the 2.26 mile marker in Morgan Township will be closed Wednesday, July 25, through Friday, July 27, both day and night. The location of the closure is between Van Crabtree Road and Big Bear Creek Road. County Engineer’s Crews will be installing a concrete pipe.

Guardrail Installation

Lake Erie Construction Company will be installing guardrail on CR-17 – Frederick Road in Bloom and Harrison Townships beginning Monday, July 23. Traffic will be maintained.

Mowing

Lucasville-Minford Road in Jefferson and Madison Townships.

Cook Road in Jefferson and Valley Township.

Glendale Road in Jefferson Township Sugar Camp Road in Porter Township.

Schwamberger Road in Vernon Township.

Sheldon-Cartro Road in Green and Vernon Township.



Comments
(0)
Comments-icon Post a Comment
No Comments Yet
Weather
Sponsored By:

Lottery
Sponsored By:

Stocks
Sponsored By:

Gas Prices
Sponsored By:

Featured Businesses
Recipes
Sponsored By: