Darren C. LeBrun, P.E., P.S., Scioto County Engineer, announced the work schedule for the week of June 5, 2017 through June 9, 2017 for the Engineer’s Department.

COUNTY CREW WORK

BERMING (weather permitting)

Haverhill – Oho Furnace Road (CR8) in Green Township , Monday, June 5th through Wednesday, June 7th will have lane restrictions from 7:00 A.M. to 500 P.M. Traffic will be maintained with the use of flaggers.

Junior Road (CR277) in Green Township, Thursday, June 8th will have lane restrictions from 7:00 A.M. to 5:00 P.M. Traffic will be maintained with the use of flaggers.

ROAD CLOSURE

Big Pete Road (CR268) in Green Township at 3.381 mile marker will be closed Tuesday, June 6th from 9:00 A.M. to 10:00 A.M. This will allow for the unloading of a concrete pipe.

MOWING

Houston Hollow – Candy Run Road in Jefferson Township.

Houston Hollow – Long Run Road in Clay and Jefferson Townships.

Rosemount – Selby Road in Clay Township.

Bonser’s Run Road in Clay and Harrison Townships.

High Street in Harrison Township.

Flatwood – Fallen Timber Road in Jefferson Township.

Millers Run – Fallen Timber Road in Jefferson, Madison and Valley Townships.

ROAD CLOSURE

Big Pete Road (CR268) in Green Township at the 3.381 mile marker will be closed Tuesday, June 6th from 9:00 A.M. to 10:00 A.M. This will allow for the unloading of a concrete pipe.

ROAD IMPROVEMENT

Allard Excavation will be raising manholes and water valves on Washington Boulevard (CR50) in Washington Township Monday, June 5th through Friday, June 9th from 7:00 A.M. to 6:00 P.M. each day. Inclusive in the work will be the intersections of sub-division streets at Washington Boulevard. Local traffic will be maintained.

VETERANS MEMORIAL HIGHWAY IMPACTS

ROAD CLOSURES

Flatwood – Fallen Timber Road (CR184) in Jefferson Township at the 0.56 to 1.03 mile markers continues to be closed through Thursday, December 1st, 2017. Portsmouth Joint Venture is excavating road embankment for construction of State Route 823 and constructing a bridge.

Ohio River Road (CR503) in Porter Township is continuing with single lane traffic through Tuesday , August 1st. Portsmouth Joint Venture is constructing mechanically stabilized earth (MSE) walls and completing a full width reconstruction of the roadway. Hastings Hill Road is fully open to traffic during the closure with single lane flagging to facilitate permanent shoulder construction along Ohio River Road.

Lucasville – Minford Road (CR28) in Madison Township continues to be closed through Tuesday, August 1st day and night. The closure allows Portsmouth Joint Venture to do mass excavation activities and reconstruction of Lucasville – Minford Road. The location is between Flowers – Ison Road (TR381) and Rases Mountain Drive (TR1570). Rases Mountain Drive is now open to thru traffic at the intersection with Lucasville – Minford Road.

Swauger Valley – Minford Road (CR31) in Harrison Township continues to have flagging operations through Saturday, June 17th. The location of the flagging is between Bond Road (TR232) and Shumway Hollow (TR234). Flaggers will be utilized to stop traffic for Artic truck crossing and construction access into the SR-823 right of way.

Please call the Engineer’s office with any questions or concerns (740-259-5541) or you can visit us on the web at SciotoCountyEngineer.org.